The following table illustrates the hazardous waste program fee surcharges included in the Executive Budget proposal for Fiscal 2003.

In addition to these surcharges, the Executive Budget also proposes a surcharge of $6,000 on all facilities that generate more than 15 TPY of hazardous wastewater. This surcharge would be applied to the current $3,000 wastewater generator fee.


HW Generated
Current
Proposed Surcharge
Combined Fee
Effective Fee
(in $per ton)
in TPY
Fee
Surcharge
Fee
Low End
Highend
15 to 25 $1,000 $4,000 $5,000 $200 $333
25 to 50 $1,000 $9,000 $10,000 $200 $400
50 to 75 $1,000 $14,000 $15,000 $200 $300
75 to 100 $1,000 $19,000 $20,000 $200 $267
100 to 500 $6,000 $24,000 $30,000 $60 $300
500 to 1000 $20,000 $80,000 $100,000 $100 $200
1000 to 2000 $40,000 $85,000 $125,000 $63 $125
2000 to 3000 $40,000 $110,000 $150,000 $50 $75
3000 to 5000 $40,000 $135,000 $175,000 $35 $58
5000 to 10000 $40,000 $160,000 $200,000 $20 $40
10000 to n $40,000 $360,000 $400,000 <$40 $40
Hazardous Wastewater
>15 TPY
$3,000 $6,000 $9,000 NA NA