Home

HAZARDOUS WASTE PROGRAM FEE SURCHARGES

March 5, 2002

The following table illustrates the hazardous waste program fee surcharges included in the Executive Budget proposal for Fiscal 2003.

In addition to these surcharges, the Executive Budget also proposes a surcharge of $6,000 on all facilities that generate more than 15 TPY of hazardous wastewater. This surcharge would be applied to the current $3,000 wastewater generator fee.

HW Generated Current Proposed Surcharge Combined Fee Effective Fee
(in $per ton)
in TPY Fee Surcharge Fee Low End Highend
15 to 25 $1,000 $4,000 $5,000 $200 $333
25 to 50 $1,000 $9,000 $10,000 $200 $400
50 to 75 $1,000 $14,000 $15,000 $200 $300
75 to 100 $1,000 $19,000 $20,000 $200 $267
100 to 500 $6,000 $24,000 $30,000 $60 $300
500 to 1000 $20,000 $80,000 $100,000 $100 $200
1000 to 2000 $40,000 $85,000 $125,000 $63 $125
2000 to 3000 $40,000 $110,000 $150,000 $50 $75
3000 to 5000 $40,000 $135,000 $175,000 $35 $58
5000 to 10000 $40,000 $160,000 $200,000 $20 $40
10000 to n $40,000 $360,000 $400,000 <$40 $40
Hazardous Wastewater
>15 TPY
$3,000 $6,000 $9,000 NA NA